Reports and printing

Available onBuilder

The Reports menu, beside the tabs at the top of the Schedule, is where the schedule comes off the screen: a printed chart for the site office, a lookahead for the trades, and reports that answer the questions you get asked every week.

Reports › Print or save as PDF… asks what to print:

Choose What you get
The whole job Every task, start to finish
Lookahead next 2, 3 or 6 weeks Only the tasks happening in those weeks
Dates I choose Any stretch you set

Then tick what to show: the trade on each task, the booked dates, the baseline. Leave out finished tasks keeps a job six months in down to what is left. If the Stage picker is set, only that stage prints.

It prints landscape: the task list on the left, the bars scaled to fit the page, the headings repeated on every page and a line for today. The link arrows are left off on purpose — on paper they turn into a tangle nobody can follow.

To get a file, choose Save as PDF as the printer. For a long job, A3 keeps it readable.

Reports › Lookahead (2, 3 or 6 weeks)… goes straight to the short version. It keeps only the tasks happening in those weeks — including ones already under way — plus the groups they sit in, so each task still reads in context.

It is the sheet for a site meeting or a trade: what is on, and who is on, over the next fortnight or so. Nobody on site needs the whole programme.

Report What it shows
Who is doing what The tasks grouped by trade. Tick to include finished work
Due and upcoming What is late, what should have started, and what starts or finishes in the next 7, 14 or 28 days
Progress Each stage: tasks, finished, percent done, planned finish and how many are late. Then every task with its status — Finished, Under way, Should have started, Late, Not started — and its delay days
Progress claims Each contract stage, the task it is linked to, that task’s percent done, the expected date, and Ready to claim once the task is 100% done
Delay report The delays recorded on this job
Export tasks to Excel Every task, in outline order, as a file Excel opens

Progress weights percent done by working days, so a finished ten-day frame counts for more than a finished one-day clean. It is the honest answer to “how far along are we?”

Progress claims also shows each stage’s amount including GST, and the total ready to claim, if you are allowed to see cash flow. Stages are linked to tasks under Contract stages. A claim that is ready and not yet sent is money you are waiting for without asking.

Export tasks to Excel has the dates, days, percent done, critical path, float, delay days, trade, booked dates and booking status, milestone and note for each task — and the cost, if you are allowed to see it.

The same questions, across the business. These only include jobs you have access to.

Report What it shows
Due and upcoming As for one job, and includes late work from the last six months
Who is doing what Each trade’s work over the next 7, 14, 28 or 56 days — booked dates where there is a booking, otherwise planned
Progress Each job side by side: site manager, tasks, finished, percent done, late, delay days and the last finish date
Delays Delays recorded in the last 30, 90, 180 or 365 days — by job, by cause, and every delay

Delays by cause is the one to look at once a quarter. If one supplier or one inspection keeps turning up, that is a conversation worth having before the next job.

Call up sheet (PDF) and Delay register (PDF) are different from the rest of the menu. The others are drawn on screen and you print them from there. These two are made as a proper PDF document — the kind you print, file, email to a site manager, or hand to someone on site.

Each one asks you a few things first:

Call up sheet Delay register
Jobs This job, or every job you can see This job, or every job you can see
Dates When the call up is due — opens on the next three weeks When the delay happened — opens on the last three months
Also Only tasks that have a trade on them; leave out the ones already confirmed —

Call up sheet lists each task with the day you have to ring by, when the trade starts, who the trade is, and whether they have confirmed. The ones not called yet are in red. Across every job it is simply a list in date order — ring these, in this order — with the job named under each task.

The call up day is worked out from the task’s lead time in weeks on the Bookings sheet: three weeks’ lead time on a task starting the 24th means ringing by the 3rd.

Delay register lists each delay with the days it cost, what kind it was, when it happened and the note — with the total days lost at the top. Across every job it is grouped by job.

Both open in a window on the page. Open in new tab gives you the PDF on its own, which is the one to use if your browser does not show PDFs inline.

Every report has Print, which prints portrait, and Download for Excel, which gives you the same rows as a file to sort, filter or send on.