The six views
Available onBuilder
Schedule & Booking is six views onto one set of tasks. They share the same underlying data, so a change in one appears in all of them.
| View | What it is for |
|---|---|
| Tasks | The list. Add, edit and check off work. |
| Schedule | The Gantt — durations, dependencies, the critical path. |
| Calendar | What is happening on which day, across every job. |
| Call up | Telling subcontractors when to come. |
| Bookings | Who has confirmed. |
| Cash flow | What the job costs, over time. |
Which to use when
Section titled “Which to use when”Planning a job — start in Tasks to get the work down, then move to Schedule to give it durations and dependencies.
Running a week — Calendar and Call up. What is on this week, and who needs telling. The Calendar is the only view that spans every job at once, so it is also the answer to “what is my site manager doing this week?”
Checking a subcontractor is coming — Bookings.
Answering “when will we be finished?” — Schedule. The Gantt is the only view that answers it, because it is the only one that understands dependencies.
Answering “when do we need the money?” — Cash flow.
Tasks are the unit
Section titled “Tasks are the unit”Everything here is a task. A task can carry:
- a duration and dates
- predecessors, so it follows other work
- a cost center and a supplier, so it connects to the estimate
- a cost, or a link to an order
- a call-up period, so the subcontractor is told in time
The more of these you fill in, the more the other five views can do. A task with a name and nothing else appears in the list and does nothing anywhere else.
How much detail
Section titled “How much detail”Enough that each task is one trade’s work in one visit, and someone could be called up for it.
| Too coarse | About right | Too fine |
|---|---|---|
Build house |
Frame — first floor |
Install stud 14 |
Twenty to sixty tasks covers most residential jobs. Beyond a couple of hundred you spend more time maintaining the schedule than the schedule saves you.
Connecting to the rest of the job
Section titled “Connecting to the rest of the job”The schedule is only worth keeping current if it connects to something. Three connections matter:
- Cost centers tie tasks back to the estimate
- Orders tie a task to what has been committed for it
- Contract stages can be linked to tasks, so reaching a stage flags the claim as due — see Contract stages