Available onBuilder

Schedule & Booking is six views onto one set of tasks. They share the same underlying data, so a change in one appears in all of them.

View What it is for
Tasks The list. Add, edit and check off work.
Schedule The Gantt — durations, dependencies, the critical path.
Calendar What is happening on which day, across every job.
Call up Telling subcontractors when to come.
Bookings Who has confirmed.
Cash flow What the job costs, over time.

Planning a job — start in Tasks to get the work down, then move to Schedule to give it durations and dependencies.

Running a weekCalendar and Call up. What is on this week, and who needs telling. The Calendar is the only view that spans every job at once, so it is also the answer to “what is my site manager doing this week?”

Checking a subcontractor is comingBookings.

Answering “when will we be finished?”Schedule. The Gantt is the only view that answers it, because it is the only one that understands dependencies.

Answering “when do we need the money?”Cash flow.

Everything here is a task. A task can carry:

  • a duration and dates
  • predecessors, so it follows other work
  • a cost center and a supplier, so it connects to the estimate
  • a cost, or a link to an order
  • a call-up period, so the subcontractor is told in time

The more of these you fill in, the more the other five views can do. A task with a name and nothing else appears in the list and does nothing anywhere else.

Enough that each task is one trade’s work in one visit, and someone could be called up for it.

Too coarse About right Too fine
Build house Frame — first floor Install stud 14

Twenty to sixty tasks covers most residential jobs. Beyond a couple of hundred you spend more time maintaining the schedule than the schedule saves you.

The schedule is only worth keeping current if it connects to something. Three connections matter:

  • Cost centers tie tasks back to the estimate
  • Orders tie a task to what has been committed for it
  • Contract stages can be linked to tasks, so reaching a stage flags the claim as due — see Contract stages