Prices, markups and GST
Available onEstimatorBuilder
An item’s Price is the cost per unit — what the work costs you, before any margin. Markup is applied on top, and is kept separate on purpose.
Where a rate comes from
Section titled “Where a rate comes from”| Source | How it behaves |
|---|---|
| A price list | Linked, so it can be refreshed later |
| A supplier’s product | Linked to that supplier’s pricing |
| A received quote | Fixed at what the subcontractor quoted |
| Typed by hand | Fixed until you change it |
Items carrying a Link to Pricelist are the ones you can update in bulk. Typed rates are invisible to every refresh, which is fine for genuine one-offs and a liability for anything recurring.
Keeping rates current
Section titled “Keeping rates current”The Items menu carries several refresh commands:
| Command | What it does |
|---|---|
| Renew prices | Updates the selected items from their linked source |
| Renew all below prices | Updates everything below the current point |
| Renew all the products of this costing | Refreshes the whole costing |
| Alert Price Changes | Flags items whose source price has moved |
Alert Price Changes is the setting worth turning on. It tells you a rate has moved rather than changing it underneath you, so you decide whether to take the new price on a job you may already have quoted.
Item markup
Section titled “Item markup”Item Markup applies to a single item. Use it for work you price differently from the rest of the job — a supply-only item you carry less margin on, or a trade you mark up harder because it carries more risk.
Item markup applies before the costing-level markups, so an item with its own markup still picks up overheads and margin on top of that. Setting 10% item markup on a line does not mean that line ends up at exactly 10% over cost in the final price.
If you want most items marked up the same way, do it at costing level and leave item markup alone. See Markups.
The GST field controls whether GST applies to an item, at the rate set on the project.
Most items carry it. The ones that typically do not are statutory fees and charges — council permits, certifier fees, some authority connections. Getting these wrong overstates your price by 10% on those lines, which is usually enough to notice but not always enough to spot.
Showing cost against actuals
Section titled “Showing cost against actuals”Show Actual Costs Columns adds committed and actual cost alongside your estimate, once orders and invoices exist.
This is how you see the estimate holding up as the job runs — allowed, committed, spent, side by side per item. It is worth turning on the moment the job is won, and leaving off while you are still estimating, when the columns are all empty.
A worked check
Section titled “A worked check”The Hendricks slab, from cost to sell:
| Concrete 18.64 m³ @ $228/m³ | $4,250 |
| Mesh 195.72 m² @ $9.40/m² | $1,840 |
| Vapour barrier 205.04 m² @ $3.10/m² | $636 |
| Bedding sand 9.32 m³ @ $62/m³ | $578 |
| Pump 1 item @ $850 | $850 |
| Slab cost | $8,154 |
| Overheads 8% | $652 |
| Margin 12% | $978 |
| Slab sell, ex GST | $9,784 |
| GST 10% | $978 |
| Slab sell, inc GST | $10,762 |
The cost line is what you would defend to a subcontractor. The sell line is what the client sees. Keeping them separate is what lets you change one without disturbing the other.
