Resources and cost
Available onBuilder
A task with a supplier and a cost stops being just a bar on a chart. It becomes the thing that drives call-ups and cash flow.
Assigning a supplier
Section titled “Assigning a supplier”Supplier and Contact say who is doing the work.
This is what makes call-up sheets and bookings work — both are built from the supplier on the task. A task with no supplier cannot be called up, because there is nobody to call.
Costing a task
Section titled “Costing a task”Select Cost Method chooses where the task’s cost comes from:
| Method | Cost comes from | Use when |
|---|---|---|
| Manual | A figure you type | No order exists yet |
| From an order | The linked purchase order | The work is ordered |
Link to Order ties the task to its purchase order.
Prefer the order
Section titled “Prefer the order”A task costed from its order is right by construction, and stays right when the order is revised. A manually costed task is a number someone typed once, and it goes stale silently.
Use manual costs while planning, before orders exist, then link the orders as they are raised.
Cost centers
Section titled “Cost centers”Cost Center ties the task back to the estimate — the same trade breakdown the BOQ uses. See Cost Centers.
With it set, the schedule and the estimate speak the same language, so you can ask what a trade was allowed, what it was committed at, and when it is scheduled, and get answers that line up.
Payment terms
Section titled “Payment terms”Payment Method and Payment Extra days describe when the money actually leaves.
This matters for cash flow. Work done in week 6 on 30-day terms is paid in week 10, and the difference between those two dates is precisely the gap a builder has to fund. Set the terms and the cash flow view times the outflow properly.
Worked example
Section titled “Worked example”The slab pour task, fully set up:
| Field | Value |
|---|---|
| Name | Slab pour — 18.6 m³ N32 |
| Duration | 1 day |
| Predecessor | Formwork and reo |
| Cost Center | 310 Slab |
| Supplier | Barwon Concrete |
| Contact | Jim Whelan |
| Cost Method | From order |
| Link to Order | PO 2026-041-03 — $5,099.92 |
| Call up (weeks) | 1 |
| Payment Method | 30 days |
That one task now drives four things:
- the Gantt knows when it happens and what follows it
- the call-up sheet tells Jim a week ahead
- bookings tracks whether he confirmed
- cash flow shows $5,099.92 leaving 30 days after the pour
None of which needed anything typed twice.
Tasks with no cost
Section titled “Tasks with no cost”Plenty of tasks legitimately have none — inspections, client walkthroughs, cure periods, waiting on a delivery.
Leave the cost blank. They still matter for the programme, which is what they are there for.
Keeping cost and schedule aligned
Section titled “Keeping cost and schedule aligned”Two habits:
- When you raise an order, link it to its task.
- When a variation is approved, add the work to the schedule and link the new order.
Skip the second and the schedule drifts from the job as variations accumulate — which is exactly when you most need it to be right.
