Keeping rates current

Available onEstimatorBuilder

A price list is only worth what its rates are worth. Keeping them current is what separates a useful list from a stale one that makes estimates confidently wrong.

A price change alert

The alert tells you which rates have moved since you last estimated.

A BOQ never changes price underneath you. When the price list moves, the item shows a price alert in the grid, and the BOQ ribbon’s Renew opens a window listing every item whose price has moved, with the old and new price and what renewing does to the job’s total. You tick the ones to take, and can undo straight afterwards. See Prices, markups and GST.

Items carrying a Link to Pricelist are the ones a refresh can reach. Rates typed by hand are invisible to every refresh, forever.

That is the practical argument for building estimates from the price list rather than typing: not the speed, but the fact that typed rates never get updated again.

Supplier schedules. Most suppliers issue updated rates periodically. Update the list when they arrive rather than filing them.

Tender results. A trade you tendered three times this year has three real market prices. That is better information than any published rate.

Your own actual costs. The most valuable source, and the one nobody uses.

Items and products supplied with SmarteBuild are read-only — you cannot change their price. You can, however, record your own price for one, and that is the price you see and the price a BOQ import uses, without the shared item changing for anyone else.

Click the item and open the drawer’s Prices tab. It shows the SmarteBuild price, lets you enter yours with Set (tick inc GST inside the price box if the figure you typed includes GST), and keeps a history of every price you have set, with who set it and from when. The My price set filter chip lists every item you have done this on, and the grid shows the price that applies to you with a “Yours” mark where it is your own.

  • From defaults to today. Set a future date to schedule a change — it shows in the list as pending and takes effect on that day.
  • Remove a price to fall back to the one before it, or to the SmarteBuild price if there is none.
  • Your price applies to your whole company group, not just the user who set it.

SmarteBuild keeps its shared prices current. When one moves, the change appears in the same Prices list, marked SmarteBuild with a lock: you can see the new price and the date it applies from, but you cannot change or remove it.

  • If you have no price of your own, the new SmarteBuild price is your price from that date — for new BOQ imports and in the BOQ’s price alert.
  • If you have a price of your own, yours still wins. The SmarteBuild rows are there so you can see the list price has risen and decide whether to update yours.
  • A SmarteBuild change dated ahead shows as from this date and takes effect on that day.

The same tab appears on your own items and on products, where it is simply a direct view of the price history that editing the price already writes. A dot on the tab means you have a price of your own on that row.

You have the data. Every finished job holds allowed, committed and actual cost per item — see Cost to date against budget.

A trade that ran over on three jobs running is not bad luck. It is a rate that needs changing.

Three completed jobs, concrete slab items:

Job Allowed Actual Variance
18 Beach Road $8,154 $8,612 +5.6%
42 Ridge Street $11,400 $12,090 +6.1%
Lot 118 Aspen $9,800 $10,240 +4.5%

Consistently 5% light. That is not three unlucky pours — the rate is wrong, or the allowance for waiting time and part-loads is missing.

Raise the concrete rate about 5%, or add a line for the extras. Either way the next estimate is right, and it was your own jobs that told you.

Once a quarter:

  1. Update from any supplier schedules received.
  2. Look at completed jobs for trades that consistently ran over.
  3. Adjust those rates.
  4. Check the rates you use most — the top twenty by frequency.
  5. Note in each entry when you checked it.

An hour, four times a year.

In the entry’s Note:

Checked Feb 2026 against Barwon schedule. Includes pump for pours over 15m³.

Six months later, that answers whether the rate is current and what it covers. A rate with no date is one nobody trusts and everybody re-checks.

Some should stay fixed:

  • A rate from a quote you accepted — that is the agreed price, not a list price
  • A rate you deliberately adjusted for a job’s particular circumstances
  • Anything on an estimate you have submitted

Where you have adjusted a rate on purpose, note why on the item. Otherwise someone refreshing the estimate later will helpfully undo your decision.

Prices that come from a supplier’s own list show their date: as at 12 Mar 2026 under the price, in the BOQ’s price list window and the product picker, and in a Price as at column you can turn on in Price lists. Past six months the price is also marked Old price, so nobody prices a job from a stale rate without knowing. Check with the supplier before you rely on it.

These dates come from the suppliers network: suppliers send us their price lists with the date the prices start, and our team checks every list before builders see it. A price with no date has none shown. Your own company’s prices are as you keep them.