Tasks
Available onBuilder
Tasks are the unit of everything in this module. The Tasks view is the list of them.
The fields
Section titled “The fields”| Field | What it does |
|---|---|
| Name | What the work is |
| Parent | Groups it under a summary task |
| Duration | How long it takes |
| Start Date | When it is planned to start |
| Actual Start Date | When it actually started |
| Actual Finish Date | When it actually finished |
| Predecessor | What has to happen first |
| Lag | Waiting time after the predecessor |
| Status | Where it is up to |
| Cost Center | Which trade it belongs to |
| Supplier | Who is doing it |
| Contact | Who at that supplier |
| Cost / Select Cost Method | What it costs |
| Link to Order | The purchase order for this work |
| Call up (weeks) | How far ahead to call the trade |
| Note | Anything else |
| Sorting Index | Order among siblings |
Structure
Section titled “Structure”Parent builds a hierarchy — a summary task with the real work underneath it.
Frame Frame — ground floor Frame — first floor Frame inspectionRoof Roof trusses Roof battens Roof tilesSummary tasks roll up their children’s dates and costs, so you get a readable overview that still has real detail behind it.
Keep it two levels for a house. Deeper structures look organised and take longer to maintain than they save.
Naming
Section titled “Naming”Name a task so that someone reading it in a call-up sheet knows what to bring.
| Weak | Better |
|---|---|
Concrete |
Slab pour — 18.6 m³ N32 |
Plumber |
Plumbing rough-in — ground floor |
Fix out |
Internal doors and architraves |
The call-up sheet carries this name to the subcontractor. Concrete on a Tuesday
tells them nothing about whether they are pouring or stripping formwork.
Actual dates
Section titled “Actual dates”Actual Start Date and Actual Finish Date are what turn the schedule from a plan into a record.
Fill them in as the job runs. Two things follow: the Gantt shows planned against actual, so slippage is visible rather than assumed; and at the end of the job you have real durations, which is the best source of estimates for the next one.
Status
Section titled “Status”Status tracks where a task is. Combined with the view filters, it is what keeps a long schedule readable:
| Filter | Shows |
|---|---|
| Hide Finished Tasks | Only what is left |
| Show Due Tasks | What is coming up |
| Show Finished Tasks | The record of what is done |
Hide Finished Tasks is the one to leave on while running a job. Six months in, two-thirds of the schedule is history and it only gets in the way.
Keeping it current
Section titled “Keeping it current”A schedule nobody updates is worse than no schedule, because people rely on it.
The minimum that works:
- Mark tasks finished as they finish.
- Enter actual start dates when work begins.
- When something slips, change it in the Schedule view so dependencies follow.
- Add tasks for variation work as it is approved.
Ten minutes a week. Step three is the one that matters — updating a date in the Tasks list changes one task, while doing it in the Gantt moves everything that depends on it. See Building a schedule.
