Comparing bids and awarding

Available onEstimatorBuilder

Quotes come back against the tender and line up on its Compare tab. The work is making sure they are actually comparable before you decide anything.

Comparing bids side by side

Compare like for like before you award anything.

Compare puts your items down the side and each subcontractor across the top. Each cell is their price for that item — their quantity times their rate — so you can see who is cheapest item by item, not just in total.

You see It means
A green cell The cheapest price for that item, when two or more subcontractors priced it
Not priced They left the item out of their quote
$0.00, in pink They put the line in but priced it at nothing
for 30 under a price They priced a different quantity from yours

Under the sheet:

  • Total for these items — what each quote comes to for the items on this tender
  • Against the budget — the difference from your estimate
  • Gaps — how many items they did not price, or priced at zero
  • Whole quote — shown when it differs, because they also priced things that are not on your tender

A total is only marked as the lowest when the subcontractor priced every item. A total with gaps is not a total.

Only each subcontractor’s latest quote is compared. If they sent more than one, the earlier ones are on the Subcontractors tab under 2 quotes.

When the quotes do not cover the same scope, a Like-for-like estimate row appears under the totals: each quote brought to the same scope, with the lowest marked. Hover over a figure to see what was added or taken off. It is an estimate for comparing, not a price anyone offered.

Check quotes with AI reads each quote’s documents and prices, paid from your company’s AI credit, and lists what it found: Left out, Allowance, Depends on, Included in another line and Not asked for. A quote with no document has only its typed prices checked, and a quote that changes afterwards is marked as changed. It can miss things or get them wrong, so check the quote itself before you rely on it.

The Compare tab, with two quotes side by side against the budget

The quote on the left totals less — and it is cheaper only because it priced the paths at $0.00, while the other left them Not priced. The Gaps row counts both, and the note underneath spells it out. Green marks the cheapest line, but no total is marked lowest, because no subcontractor priced everything.

Before comparing totals, check each bid covers the same work.

Check Why
Every item priced? A gap makes a bid look cheap
Exclusions? Read their document, not just the total
Quantities as sent? A bidder who re-measured may have found something
Conditions? Payment terms, retention, insurance, minimum call-outs
Prelims and access? Scaffold, hoisting, cleaning — who is allowing for it

The lowest bid is often the one that excluded the most. That is not dishonesty, usually — it is a subcontractor pricing exactly what they read.

Three bids for the Hendricks roofing package:

Bidder Total Notes
A $17,240 All items priced. Excludes scaffold.
B $18,600 All items priced. Includes scaffold.
C $16,900 Sarking not priced. Excludes scaffold and edge protection.

C looks cheapest and is not. Add sarking at around $1,400 and C is $18,300 — and still excludes edge protection.

Scaffold is $1,900 if you supply it. So the real comparison is:

Bidder Comparable total
A $19,140
B $18,600
C $20,200+

B, which looked the most expensive, is the cheapest — and is the only bid where nobody has to work out who is bringing the scaffold.

Once you have chosen, press Select this quote under that subcontractor’s column on Compare, or Award on their row in the tender list. For every item they priced, their quantity, their product and their quoted price go into your estimate, replacing what was there. (From the list you can also award without touching the estimate.)

Anyone else selected on those items is cleared at the same time, so the estimate and the tender always agree on who won each item. The winner’s column shows Selected, and the tender’s progress line moves to Awarded.

The items pick up the quoted rates and carry a Related bid link back to the source. The winner’s own quote page changes too: it shows Accepted and locks, so they cannot change a price that is now in your estimate — it tells them to contact you instead.

That link is what answers “who quoted this and when?” six months later, without anyone opening a mailbox. It also means the purchase order you eventually raise carries the rate that was actually quoted.

While you are there, set the supplier on the items to the winning bidder. It takes a moment now and saves assigning them by hand at ordering. See Suppliers and products.

Tell the unsuccessful bidders, briefly and promptly.

It costs a short email and it is the reason they price your next job. A subcontractor who prices three of your packages and never hears back on any of them stops answering.

You do not have to give them the numbers. “Thanks for pricing this — we have gone with another contractor this time, but I will have the next one out to you” is enough.

The tender keeps who was invited, what they were sent, when, and what came back.

That is what you want when a subcontractor says the scope was different from what they priced — the package they were sent is attached to the job, not reconstructed from memory.

You can re-tender. Before you do, work out why: too little time, the wrong bidders, an unclear package, or a genuinely expensive piece of work.

Re-tendering the same package to the same people with the same information gets the same answer.