Call-up sheets

Available onBuilder

A call-up sheet tells a subcontractor when they are needed. The Call up view generates them from the schedule, so the dates come from the programme rather than from somebody’s memory.

Call up (weeks) on a task is how far ahead that trade needs telling.

Set it per task, because trades differ enormously:

Trade Typical notice
Concrete 1 week
Carpenter 2 weeks
Plasterer 2 weeks
Roof tiler 2 weeks
Cabinetmaker 6 weeks — it is a manufacturing lead time
Windows 8 weeks — ordered, not called up
Crane 1 week, and confirm the day before

Ask each of your regular subcontractors what notice they want and set it once. It is the difference between a trade turning up and a trade being on someone else’s job.

The Call up view shows what is due to be called based on each task’s notice period and its scheduled start.

A workable routine, same time each week:

  1. Open the Call up view.
  2. Work down what is due.
  3. Send each call-up.
  4. Note the ones that need confirming — see Bookings.
  5. Chase last week’s unconfirmed ones.

Twenty minutes on a Monday morning, across every job.

Four things, and the sheet carries them from the task:

  • What the work is — the task name, which is why naming tasks properly matters
  • When — the date, and how long you have allowed
  • Where — the site address, from the project
  • Anything they need to know — access, materials, who else is on site

Concrete, Tuesday is not a call-up. Slab pour, 18.6 m³ N32, Tuesday 14 Oct from 7am, 18 Beach Road Torquay, pump booked, access via rear lane is one.

A call-up that has been sent is not a trade that is coming. Confirmations are tracked in Bookings, and the gap between sent and confirmed is where lost days live.

If a task moves after its call-up has gone out, tell the trade — and say what changed rather than just sending a new date.

A subcontractor who receives a second sheet with a different date and no explanation often assumes the first was wrong, or ignores it. One who is told “the frame inspection slipped, so you are now Thursday not Tuesday” re-plans around you.

A call-up is not an order. The order commits the money and the scope; the call-up says when to come.

Both usually go to the same subcontractor for the same work, and both are needed. A trade with an order but no call-up does not know when; a trade with a call-up but no order has no agreed price.